Legislation Details

File #: 22-211    Version: 1 Name:
Type: Consent Item Status: Passed
File created: 3/14/2022 In control: City Council/Public Finance and Economic Development Authority/Parking Authority
On agenda: 4/18/2022 Final action: 4/18/2022
Title: SUBJECT: Approval of Additional Contingency in the Amount of $6,589.50 for Additional Work Which is Reflected in the Final Change Order #4 with Agee Construction Corporation for V Street Improvements - 16th Street to 18th Street, Project No. 117038 Which will be the Final Increase for the Project in Order to Close out the Project REPORT IN BRIEF Considers approving an increase to the contingency in the amount of $6,589.50 for City Project No. 117038 - V Street Improvements, 16th Street to 18th Street and Change Order #4 with Agee Construction Corporation. This increase will be the Final increase for the project in order to close out the project. RECOMMENDATION City Council - Adopt a motion authorizing the City Manager or Deputy City Manager to execute the necessary documents and to approve change orders with Agee Construction Corporation up to a total contingency amount of $61,703.03 including an increase in contingency of $6,589.50.
Attachments: 1. CCO1 Executed.PDF, 2. CCO2 Executed.pdf, 3. CCO3 Executed.pdf, 4. CCO4 .pdf

Report Prepared by: Paul Flores, EIT, Assistant Engineer

 

Title

SUBJECT: Approval of Additional Contingency in the Amount of $6,589.50 for Additional Work Which is Reflected in the Final Change Order #4 with Agee Construction Corporation for V Street Improvements - 16th Street to 18th Street, Project No. 117038 Which will be the Final Increase for the Project in Order to Close out the Project

 

REPORT IN BRIEF

Considers approving an increase to the contingency in the amount of $6,589.50 for City Project No. 117038 - V Street Improvements, 16th Street to 18th Street and Change Order #4 with Agee Construction Corporation. This increase will be the Final increase for the project in order to close out the project.

 

RECOMMENDATION

City Council - Adopt a motion authorizing the City Manager or Deputy City Manager to execute the necessary documents and to approve change orders with Agee Construction Corporation up to a total contingency amount of $61,703.03 including an increase in contingency of $6,589.50.

 

Body

ALTERNATIVES

1.  Approve, as recommended by staff; or,

2.  Approve, subject to conditions other than recommended by staff (identify specific findings and/or conditions amended to be addressed in the motion); or,

3.  Deny; or,

4.  Refer to staff for reconsideration of specific items (specific items to be addressed in the motion); or,

5.  Continue to a future meeting (date and time to be specified in the motion).

 

AUTHORITY

Charter of the City of Merced, Article XI, Section 1109 - Contracts on Public Works, and Merced Municipal Code Chapter 3.04, Article IV - Public Works Contracts.

 

CITY COUNCIL PRIORITIES

As provided for in the 2021-22 Adopted Budget.

 

DISCUSSION

This increase will be the final increase for the project in order to close out the project. The increase in the contingency for the V Street Improvements - 16th Street to 18th Street project by $6,589.50 is due to the following:

 

1.                     Additional AC cutback work required for new driveway transitions.

 

The initial contingency amount of $55,888.30 was paid to the Agee Construction Corporation for extra work by Change Order #1,2 and 3. The extra work totaled $55,113.53 and consisted of the following:

 

Change Order1: $32,501.33

1.                     Additional concrete work,

2.                     Replace traffic conduit to signal,

3.                     Add green-thermo bike lane markings,

4.                     Additional signage, and,

5.                     Red curbing.

 

Change Order2: $18,215.85

1.                     Additional grading, and,

2.                     Additional cost for increased oil index pricing.

 

Change Order 3: $4,396.35

1.                     Install bollards

 

The following was approved by the City Council on July 6, 2022:

 

The work to be performed includes but not limited to the grinding and disposal of asphalt paving, Full Depth Reclamation (FDR) installation of 3-inch asphalt paving, ADA ramps, sidewalk, curb & gutter, alley and commercial driveway approaches and traffic markings.

 

Staff prepared plans and specifications, and bids were opened on June 1, 2021, with a total of six bid submissions:

 

1.                     TBS Contractors.                     $ 702,899.52

2.                     DOD Construction                     $ 626,387.75

3.                     Avison Construction, Inc.                     $ 566,264.00

4.                     Machado and Sons                     $ 719,863.39

5.                     Agee Construction Corporation                     $ 558,883.00

6.                     United Pavement Maintenance, Inc.                      $ 627,108.37

 

The engineer’s estimate for construction was $589,571.50

 

The following is the proposed budget for the project:

    Agee Construction Corporation

    $  558,883.00

    Contingency

    $    55,888.30

    Engineering, Testing & Inspection

    $    16,766.49

      TOTAL:

    $  631,537.79

 

 

IMPACT ON CITY RESOURCES

This project was established as a Capital Improvement Project to be funded by Measure V, and Sewer Enterprise funds. Funding is available to complete the project.

 

ATTACHMENTS

1.  CCO1 Executed

2.  CCO2 Executed

3.  CCO3 Executed

4.  CCO4