File #: 24-1209    Version: 1 Name:
Type: Consent Item Status: Passed
File created: 12/4/2024 In control: City Council/Public Finance and Economic Development Authority/Parking Authority
On agenda: 1/6/2025 Final action: 1/6/2025
Title: SUBJECT: Approval of an Increase in Contingency in the Amount of $73,089.83 for Additional Unanticipated Work Reflected in Contract Change Order No. 7 with Mid Cal Pipeline & Utilities, Inc. for the Orchard Lane Sewer Relocation Project No. CP190025 REPORT IN BRIEF Considers approving proposed Contract Change Order No. 7 for unanticipated work, with an increase in contingency in the amount of $73,089.83 for Project No. CP190025 Orchard Lane Sewer Relocation Project. RECOMMENDATION City Council - Adopt a motion: A. Approving proposed Contract Change Order No. 7 with an increase in contingency of $73,089.83 for a total contingency amount of $160,713.33, which is approximately 18.34% of the original contract amount; and, B. Authorizing the City Manager to execute the necessary documents.
Attachments: 1. Executed Original Contract.pdf, 2. Executed Change Orders No. 1 - 6, 3. Proposed Change Order No. 7.pdf
Report Prepared by: John Ainsworth, Temporary Senior Engineer, Engineering Department

Title
SUBJECT: Approval of an Increase in Contingency in the Amount of $73,089.83 for Additional Unanticipated Work Reflected in Contract Change Order No. 7 with Mid Cal Pipeline & Utilities, Inc. for the Orchard Lane Sewer Relocation Project No. CP190025

REPORT IN BRIEF
Considers approving proposed Contract Change Order No. 7 for unanticipated work, with an increase in contingency in the amount of $73,089.83 for Project No. CP190025 Orchard Lane Sewer Relocation Project.

RECOMMENDATION
City Council - Adopt a motion:

A. Approving proposed Contract Change Order No. 7 with an increase in contingency of $73,089.83 for a total contingency amount of $160,713.33, which is approximately 18.34% of the original contract amount; and,

B. Authorizing the City Manager to execute the necessary documents.

Body
ALTERNATIVES
1. Approve, as recommended by Staff; or,
2. Approve, subject to conditions other than recommended by Staff (identify specific
findings and/or conditions amended to be addressed in the motion); or,
3. Deny; or,
4. Refer to staff for reconsideration of specific items (specific items to be addressed in the motion); or
5. Continue to a future meeting (date and time to be specified in the motion).

AUTHORITY
Charter of the City of Merced, Article XI, Section 1109 - Contracts on Public Works, and Merced Municipal Code Chapter 3.04, Article IV - Public Works Contracts.

CITY COUNCIL PRIORITIES
As provided for in the 2024-2025 Adopted Budget.

DISCUSSION
Staff prepared plans and specifications, the project was advertised for bids, and City Council awarded the project to Mid Cal Pipeline & Utilities, Inc., in the amount of $876,235.00 on April 17, 2023.

City staff applied for and received an Encroachment Permit from Caltrans for the Jack & Bore under State Highway 99 and an Agreement with Union Pacific Railroad for the Jack & Bore under the railroad tracks. A...

Click here for full text