Report Prepared by: Rhett Williams, Airport Manager, Merced Yosemite Regional Airport
Title
SUBJECT: Airport Manager Report
Report in Brief:
Summary of key tasks completed by the Merced Airport staff.
RECOMMENDATION
Information only-no action required.
Body
DISCUSSION
AIRPORT TERMINAL REPLACEMENT PROJECT
Airport and Engineering staff continue to regularly meet with the contractor Diede Construction and design consultants Mead & Hunt focusing on construction progress, project schedule and changes as needed.
Economic Development Associate Karen Baker continues coordinating with Mead & Hunt regarding interior design, functionality, and furnishing. The desired outcome of the interior is to be welcoming and reflect the culture of the San Joaquin Valley and City of Merced.
As construction progresses, staff anticipates the terminal project to be completed by Fall of 2025 (weather permitting.)
Terminal replacement for June is currently at 75% to date of work. Finish work of the interior (counters, sinks, wall boards) and exterior siding has been completed along with permanent windows have been installed. PA system has been installed and City staff went through a training course provided by the vendor. Card lock door system has been installed for electronic door access.
AIRPORT ADMINISTRATION
Public Outreach: Tours were provided, and positive feedback was received.
Airport Manager Williams spoke at the Merced Kiwanis Club in May about the Airport and New Terminal.
Airport Manager Williams whet to Washington DC as part of the "One Voice" delegation of local representatives representing Merced County through Merced County Association of Governments, to speak with the FAA with regards to future airport funding. Williams also met with the Department of Transportation regarding the EAS program.
AIRPORT IMPROVEMENT PROJECTS
The FAA RTR project is 85% completed. The FAA will need to connect to MID along Macready Drive to complete the installatio...