Skip to main content
File #: 25-721    Version: 1 Name:
Type: Action Items Status: Agenda Ready
File created: 7/25/2025 In control: City Council/Public Finance and Economic Development Authority/Parking Authority
On agenda: 8/4/2025 Final action:
Title: SUBJECT: Award Bid to Juarez Brothers General Engineering, Inc., for Santa Fe Strip Park Sidewalk Yosemite to Black Rascal, Project Number CP220021, and the Santa Fe Strip Park Speed Table Project CP230004, in the Amount of $519,879.33 REPORT IN BRIEF Considers awarding a Construction Contract to Juarez Brothers General Engineering, Inc, in the amount of $519,879.33 for the Santa Fe Strip Park Sidewalk Yosemite to Black Rascal and Santa Fe Strip Park Speed Table, Project Numbers CP220021 & CP230004. RECOMMENDATION City Council - Adopt a motion: A. Awarding the Construction Contract for Santa Fe Strip Park Sidewalk Yosemite to Black Rascal, Projects CP220021 & CP230004, to Juarez Brothers General Engineering, Inc, in the amount of $519,879.33; and, B. Authorizing the City Manager to execute the necessary documents and to approve change orders not to exceed 15% of the total contract.
Attachments: 1. Bid Results, 2. Location Map.pdf, 3. Construction Contract.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Report Prepared by: Rom Robinson, Assistant Engineer, Engineering Department

Title
SUBJECT: Award Bid to Juarez Brothers General Engineering, Inc., for Santa Fe Strip Park Sidewalk Yosemite to Black Rascal, Project Number CP220021, and the Santa Fe Strip Park Speed Table Project CP230004, in the Amount of $519,879.33

REPORT IN BRIEF
Considers awarding a Construction Contract to Juarez Brothers General Engineering, Inc, in the amount of $519,879.33 for the Santa Fe Strip Park Sidewalk Yosemite to Black Rascal and Santa Fe Strip Park Speed Table, Project Numbers CP220021 & CP230004.

RECOMMENDATION
City Council - Adopt a motion:

A. Awarding the Construction Contract for Santa Fe Strip Park Sidewalk Yosemite to Black Rascal, Projects CP220021 & CP230004, to Juarez Brothers General Engineering, Inc, in the amount of $519,879.33; and,

B. Authorizing the City Manager to execute the necessary documents and to approve change orders not to exceed 15% of the total contract.

Body
ALTERNATIVES
1. Approve, as recommended by staff; or,
2. Approve, subject to conditions other than recommended by staff (identify specific findings and/or conditions amended to be addressed in the motion); or,
3. Deny; or,
4. Refer to staff for reconsideration of specific items (specific items to be addressed in the motion); or,
5. Continue to a future meeting (date and time to be specified in the motion).

AUTHORITY
Charter of the City of Merced, Article XI, Section 1109 - Contracts on Public Works.

Merced Municipal Code Chapter 3.04, Article IV - Public Works Contracts.

CITY COUNCIL PRIORITIES
As provided for in the 2025-26 Adopted Budget.

DISCUSSION
The Santa Fe Strip Park Sidewalk Replacement Project consists of two separate projects.

* Santa Fe Strip Park Sidewalk Yosemite to Black Rascal, Project Number CP220021 was established during the Fiscal Year 2021-2022 as a Measure V Project. The project scope includes:

o Repairing damaged sidewalk and bike paths, removing dis...

Click here for full text