File #: 25-916    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 10/9/2025 In control: City Council/Public Finance and Economic Development Authority/Parking Authority
On agenda: 11/17/2025 Final action:
Title: SUBJECT: Approval of Additional Contingency in the Amount of $179,197.59 for Additional Work Which is Reflected in Change Orders 2 and 3 with American Paving Co. for the Main Street Directional, Project No. CP230014 REPORT IN BRIEF Considers approving an increase to the contingency in the amount of $179,197.59 for Project No. CP230014 - Main Street Directional for the extra work reflected in Change Orders 2 and 3. RECOMMENDATION City Council - Adopt a motion: A. Approving the increase in contingency in the amount $179,197.59, for a total contingency amount of $324,068.30, which is approximately 33.55% of the original agreement amount for the extra work reflected in Contract Change Orders 2 and 3; and, B. Authorizing the City Manager to execute the necessary documents.
Attachments: 1. Executed Original Agreement, 2. Executed Change Order 1, 3. Proposed Change Order 2, 4. Proposed Change Order 3
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Report Prepared by: Rom Robinson, Assistant Engineer, Engineering

Title
SUBJECT: Approval of Additional Contingency in the Amount of $179,197.59 for Additional Work Which is Reflected in Change Orders 2 and 3 with American Paving Co. for the Main Street Directional, Project No. CP230014

REPORT IN BRIEF
Considers approving an increase to the contingency in the amount of $179,197.59 for Project No. CP230014 - Main Street Directional for the extra work reflected in Change Orders 2 and 3.

RECOMMENDATION
City Council - Adopt a motion:

A. Approving the increase in contingency in the amount $179,197.59, for a total contingency amount of $324,068.30, which is approximately 33.55% of the original agreement amount for the extra work reflected in Contract Change Orders 2 and 3; and,

B. Authorizing the City Manager to execute the necessary documents.

Body
ALTERNATIVES
1. Approve, as recommended by staff; or,
2. Approve subject to conditions other than recommended by staff (identify specific findings and/or conditions amended to be addressed in the motion); or,
3. Deny; or,
4. Refer to staff for reconsideration of specific items (specific items to be addressed in the motion); or,
5. Continue to a future meeting (date and time to be specified in the motion)

AUTHORITY
Charter of the City of Merced, Article XI, section 1109 - Contract on Public Works

Merced Municipal Code Chapter 3.04, Article IV - Public Works Contract.

CITY COUNCIL PRIORITIES
As provided for in the 2025-26 Adopted Budget.

DISCUSSION
At the August 5, 2024, City Council meeting, Council approved allocating $300,000 of the City's annual RSTP (Regional Surface Transportation Program) allocation to CP230014 - Main St One-Way. This additional funding would allow for ARPA to be utilized on projects that cannot use street funding sources.

At the November 4, 2024, Council meeting, Council approved reallocating a total of $208,041 of ARPA funding to CP220073 - Bob Hart Square Expansion to close the ...