File #: 24-826    Version: 1 Name:
Type: Consent Item Status: Passed
File created: 8/16/2024 In control: City Council/Public Finance and Economic Development Authority/Parking Authority
On agenda: 10/21/2024 Final action: 10/21/2024
Title: SUBJECT: Approval of Additional Contingency in the Amount of $603,748.13 for Additional Unanticipated Work on the WWTF Phase VI Headworks Project Number CP230035 REPORT IN BRIEF Considers approving proposed change order from GSE Construction Inc., with additional contingency in the amount of $603,748.13 for Project No. CP230035 - WWTF Phase VI Headworks. RECOMMENDATION City Council - Adopt a motion: A. Approving the Proposed Change Order from GSE Construction, Inc., with additional contingency amount of $603,748.13, for a total contingency amount of $919,018.13, which is approximately 29.15% of the original contract amount; and, B. Authorizing the City Manager to execute the necessary documents.
Attachments: 1. Executed Contract Change Order 1, 2. Executed Contract Change Order 2, 3. Executed Contract Change Order 3, 4. Pending Execution Contract Change Order 4, 5. Pending Contract Change Order 5, 6. Original Executed Contract
Report Prepared by: Rick Maddox, P.E., Interim City Engineer

Title
SUBJECT: Approval of Additional Contingency in the Amount of $603,748.13 for Additional Unanticipated Work on the WWTF Phase VI Headworks Project Number CP230035

REPORT IN BRIEF
Considers approving proposed change order from GSE Construction Inc., with additional contingency in the amount of $603,748.13 for Project No. CP230035 - WWTF Phase VI Headworks.

RECOMMENDATION
City Council - Adopt a motion:

A. Approving the Proposed Change Order from GSE Construction, Inc., with additional contingency amount of $603,748.13, for a total contingency amount of $919,018.13, which is approximately 29.15% of the original contract amount; and,

B. Authorizing the City Manager to execute the necessary documents.

Body
ALTERNATIVES
1. Approve, as recommended by staff; or,
2. Approve, subject to conditions other than recommended by staff (identify specific findings and/or conditions amended to be addressed in the motion); or,
3. Deny; or,
4. Refer to staff for reconsideration of specific items (specific items to be addressed in the motion); or,
5. Continue to a future meeting (date and time to be specified in the motion).

AUTHORITY
Charter of the City of Merced, Article XI, Section 1109 - Contracts on Public Works, and Merced Municipal Code Chapter 3.04, Article IV - Public Works Contracts.

CITY COUNCIL PRIORITIES
As provided for in the 2024-25 Adopted Budget.

DISCUSSION
On June 20, 2023, Council awarded the WWTF Phase VI Headworks project to GSE Construction Inc., in the amount of $3,152,700.00 with a 10% contingency of $315,270.00.

The work to be done consisted of construction of a new influent flow meter manhole; and new mechanical screens, washer/compactors, grit removal baffles, new equipment hatches, flap gates, vent piping, electrical, concrete repair, and coating for the Headworks Improvements. After acquiring materials, the contractor began work on May 13, 2024. After cleaning the i...

Click here for full text