Report Prepared by: Ken F. Elwin, PE, Director of Public Works
Title
SUBJECT: Approval of an Eighth Amendment to the Professional Services Agreement with Stantec Consulting Services, Inc., for the Wastewater Collection System Master Plan (WCSMP) Update Environmental Impact Report (EIR) Project CP130059 for a not to Exceed Additional Amount of $50,348 for a Total Contract not to Exceed Amount of $1,073,198
REPORT IN BRIEF
Considers approving an Eighth Amendment to a Professional Services Agreement with Stantec Consulting Services, Inc., to include cultural resources tasks as part of the preparation of a draft and final Recirculated Environmental Impact Report (REIR).
RECOMMENDATION
City Council - Adopt a motion:
A. Approving an eighth amendment to professional services agreement with Stantec Consulting Services, Inc., in the additional amount of $50,348 for the City of Merced Wastewater Collection System Master Plan Update Environmental Impact Report (EIR); and,
B. Authorizing the City Manager to execute the necessary documents.
Body
ALTERNATIVES
1. Approve, as recommended by staff; or,
2. Approve, subject to conditions other than recommended by staff (identify specific findings and/or conditions amended to be addressed in the motion); or,
3. Deny; or,
4. Refer to staff for reconsideration of specific items (specific items to be addressed in the motion); or,
5. Continue to a future meeting (date and time to be specified in the motion).
AUTHORITY
Charter of the City of Merced, Section 200 et seq.
Services with an estimated value greater than $38,000.00 are made by written contract in accordance with Merced Municipal Code, Title 3 - Revenue and Finance, Chapter 3.04.
CITY COUNCIL PRIORITIES
As provided for in the Fiscal Year 2024/2025 Adopted Budget.
DISCUSSION
In April 2013, the City of Merced (City) authorized Stantec Consulting Services, Inc. (Stantec) to prepare an update to the City's 2007 Draft Sewer Master Plan. The scope of that effo...