Title: SUBJECT: Award Bid to Taylor Backhoe Service, Inc., for the CMAQ Sidewalk Infill on Alexander Avenue Project 114051 REPORT IN BRIEF Consider awarding a construction contract in the amount of $247,121.90 for the construction of sidewalk infill along portions of Alexander Avenue. RECOMMENDATION City Council - Adopt a motion: A. Awarding the bid for the CMAQ Sidewalk Infill on Alexander Avenue Project 114051, to Taylor Backhoe Service, Inc., in the amount of $247,121.90; and, B. Authorizing the City Manager to execute the necessary documents and to approve change orders not to exceed 10% of the total contract.
Attachments: 1. Location Map, 2. Bid Results, 3. Construction Contract
Report Prepared by: John C. Sagin, Jr., AIA, Principal Architect, Engineering Dept.

Title
SUBJECT: Award Bid to Taylor Backhoe Service, Inc., for the CMAQ Sidewalk Infill on Alexander Avenue Project 114051

REPORT IN BRIEF
Consider awarding a construction contract in the amount of $247,121.90 for the construction of sidewalk infill along portions of Alexander Avenue.

RECOMMENDATION
City Council - Adopt a motion:

A. Awarding the bid for the CMAQ Sidewalk Infill on Alexander Avenue Project 114051, to Taylor Backhoe Service, Inc., in the amount of $247,121.90; and,

B. Authorizing the City Manager to execute the necessary documents and to approve change orders not to exceed 10% of the total contract.

Body
ALTERNATIVES
1. Approve, as recommended by staff; or,
2. Approve, subject to conditions other than recommended by staff (identify specific findings and/or conditions amended to be addressed in the motion); or,
3. Deny; or,
4. Refer to staff for reconsideration of specific items (specific items to be addressed in the motion); or,
5. Continue to a future meeting (date and time to be specified in the motion).

AUTHORITY
Charter of the City of Merced, Article XI, Section 1109 - Contracts on Public Works, and Merced Municipal Code Chapter 3.04, Article IV - Public Works Contracts. Every project involving an expenditure of more than sixty-three thousand and fifty-four dollars ($63,054) for the construction or improvements of public buildings, works, streets, drains, sewers, utilities, parks, and playgrounds shall be let by contract to the lowest responsive and responsible bidder after notice by publication in the official newspaper by one or more insertions, the first of which shall be at least ten days before the time for opening bids.

CITY COUNCIL PRIORITIES
As provided for in the 2016-17 Adopted Budget.

DISCUSSION
The work to be done consists, in general, of the installation of 6,000 feet of missing sidewalk, 35 driveway approaches, 6 ADA ramps, a...