File #: 18-096    Version: 1 Name:
Type: Consent Item Status: Passed
File created: 2/21/2018 In control: City Council/Public Finance and Economic Development Authority/Parking Authority/Successor Agency to the Redevelopment Agency
On agenda: 4/2/2018 Final action: 4/2/2018
Title: SUBJECT: Amendment Modification Summary (E-76) for Active Transportation Program (ATP) Cycle 1 Grant for the Construction Phase of the Highway 59 Multi-Use Pathway Crossing Project 115047 REPORT IN BRIEF Consideration of acceptance and appropriation of $834,000.00 in ATP Grant funding for the construction costs associated with the pedestrian crossing project on Highway 59 at the BNSF RR crossing. RECOMMENDATION City Council - Adopt a motion: A. Accepting grant revenue from ATP (Caltrans) for construction cost associated with the pedestrian crossing project on Highway 59 at the BNSF RR crossing; increasing revenue account 450-1104-321-17-00, Proj 115047 in the amount of $834,000; and, B. Appropriating the same to account 450-1104-637-65-00- Project 115047 Highway 59 Multi Use Pathway Crossing; and, C. Approving the use of pooled cash until reimbursement from the grant is received; and, D. Authorizing the City Manager or Assistant City Manager to execute the necessary documen...
Attachments: 1. Location Map, 2. E-76 CML-5085(045)
Report Prepared by: John Ainsworth, Temporary Senior Engineer, Engineering Dept.

Title
SUBJECT: Amendment Modification Summary (E-76) for Active Transportation Program (ATP) Cycle 1 Grant for the Construction Phase of the Highway 59 Multi-Use Pathway Crossing Project 115047

REPORT IN BRIEF
Consideration of acceptance and appropriation of $834,000.00 in ATP Grant funding for the construction costs associated with the pedestrian crossing project on Highway 59 at the BNSF RR crossing.

RECOMMENDATION
City Council - Adopt a motion:

A. Accepting grant revenue from ATP (Caltrans) for construction cost associated with the pedestrian crossing project on Highway 59 at the BNSF RR crossing; increasing revenue account 450-1104-321-17-00, Proj 115047 in the amount of $834,000; and,

B. Appropriating the same to account 450-1104-637-65-00- Project 115047 Highway 59 Multi Use Pathway Crossing; and,

C. Approving the use of pooled cash until reimbursement from the grant is received; and,

D. Authorizing the City Manager or Assistant City Manager to execute the necessary documents.

Body
ALTERNATIVES
1. Approve, as recommended by staff; or,
2. Approve, subject to conditions other than recommended by staff (identify specific findings and/or conditions amended to be addressed in the motion); or,
3. Deny; or,
4. Refer to staff for reconsideration of specific items (specific items to be addressed in the motion); or,
5. Continue to a future meeting (date and time to be specified in the motion).

AUTHORITY
Charter of the City of Merced, Section 200 et seq.

Caltrans Procedures for Administering Local Grant Projects in the State Transportation Improvement Program (STIP) are used to comply with the changes to the programming and funding statutes brought about by Chapter 622 of the Statutes of 1997 (SB 45, Kopp). The procedures have been modified to remain consistent with and complimentary to the various guidelines and policies adopted by the California Transportation C...