Report Prepared by: Michael R. Beltran II, PE, City Engineer
Title
SUBJECT: Award of Bid and Approval of Construction Contract with Rolfe Construction Company, Inc., in the Amount of $1,839,263.00, for a Sewer Funded Project for the Gerard Avenue Sewer from Highway 99 to Water Well 10-R2 (Kibby Road), Project No. 117020
REPORT IN BRIEF
Considers awarding a construction contract in the amount of $1,839,263.00 funded by Sewer Enterprise funds for City Project No. 117020 - Gerard Avenue Sewer from Highway 99 to Water Well 10-R2 (Kibby Road).
RECOMMENDATION
City Council - Adopt a motion:
A. Awarding the Gerard Avenue sewer from Highway 99 to Water Well 10-R2 (Kibby Road), Project 117020, to Rolfe Construction Company, Inc., in the amount of $1,839,263.00 and,
B. Authorizing the Interim City Manager to execute the necessary documents and to approve change orders not to exceed 10% of the total contract.
Body
ALTERNATIVES
1. Approve, as recommended by staff; or,
2. Approve, subject to conditions other than recommended by staff (identify specific findings and/or conditions amended to be addressed in the motion); or,
3. Deny; or,
4. Refer to staff for reconsideration of specific items (specific items to be addressed in the motion); or,
5. Continue to a future meeting (date and time to be specified in the motion).
AUTHORITY
Charter of the City of Merced, Article XI, Section 1109 - Contracts on Public Works, and Merced Municipal Code Chapter 3.04, Article IV - Public Works Contracts.
CITY COUNCIL PRIORITIES
As provided for in the 2020-21 Adopted Budget.
DISCUSSION
The work to be done consists of the removal of the existing sewer trunk main and the installation of a new sewer trunk main on/adjacent to Gerard Avenue from Highway 99 to Well Site 10-R2 (Kibby Road).
Staff prepared plans and specifications, and bids were opened on October 6, 2020, with a total of three (3) bid submissions:
1. Rolfe Construction Company, Inc. $ 1,839,263.00
2. Mid Cal Pipeline Utilities, Inc. $ 2,406,799.00
3. Mozingo Construction, Inc. $ 3,655,044.00
The engineer’s estimate for construction was $1,673,860.50
The following is the proposed budget for the project:
Construction |
$ $1,839,263.00 |
Contingency |
$ $ 183,926.30 |
Engineering, Testing & Inspection |
$ $ 70,000.00 |
TOTAL: |
$ $2,093,189.30 |
This project will require the contractor to notify property owners by door hangers and barricades of when work will be done to ensure the residents and business owners are aware of the construction.
IMPACT ON CITY RESOURCES
This project was established as a Capital Improvement Project to be funded with Sewer Enterprise funds. Funding is available to complete the project.
ATTACHMENTS
1. Location Map
2. Bid Results
3. Construction Contract