File #: 23-1085    Version: 1 Name:
Type: Report Item Status: Passed
File created: 12/4/2023 In control: City Council/Public Finance and Economic Development Authority/Parking Authority/Successor Agency to the Redevelopment Agency
On agenda: 1/2/2024 Final action: 1/2/2024
Title: SUBJECT: Request Authorization to Waive the Competitive Bidding Process for Community Park 42 (CP-42) and Single Source the Remainder of the Work as Approved by the Merced City Council for the Construction of the Second Phase of Development at Community Park 42 (CP-42), Including the Approval of Contract Change Order No. 2 on Project Number CP220061 - Community Park 42 (CP-42) in the Amount of $1,532,539 for Additional Work REPORT IN BRIEF Staff request authorization to waive the competitive bidding requirements for CP-42 and single source the remainder of the work as approved by City Council for the construction of the second phase of development at CP-42, and request Council approve Contract Change Order No. 2 for additional site grading; installing the electrical for irrigation controls, lights, and field lights; installing storm drain and irrigation for the two extra soccer fields and landscaping, sidewalks, and basketball courts; and contract quantity adjustments in the amount o...
Sponsors: Joe Cardoso
Attachments: 1. Contract Change Order No 2, 2. Original Contract & Change Order No. 1.pdf, 3. Presentation.pdf
Report Prepared by: Christopher Jensen, Director of Parks & Community Services & Joe Cardoso, P.L.S., City Surveyor, Engineering Department

Title
SUBJECT: Request Authorization to Waive the Competitive Bidding Process for Community Park 42 (CP-42) and Single Source the Remainder of the Work as Approved by the Merced City Council for the Construction of the Second Phase of Development at Community Park 42 (CP-42), Including the Approval of Contract Change Order No. 2 on Project Number CP220061 - Community Park 42 (CP-42) in the Amount of $1,532,539 for Additional Work

REPORT IN BRIEF
Staff request authorization to waive the competitive bidding requirements for CP-42 and single source the remainder of the work as approved by City Council for the construction of the second phase of development at CP-42, and request Council approve Contract Change Order No. 2 for additional site grading; installing the electrical for irrigation controls, lights, and field lights; installing storm drain and irrigation for the two extra soccer fields and landscaping, sidewalks, and basketball courts; and contract quantity adjustments in the amount of $1,532,539.

RECOMMENDATION
City Council - Adopt a motion:

A. Waiving the City's competitive bidding requirement as permitted by Merced Municipal Code Section 3.04.210; and,

B. Approving Contract Change Order No. 2 with American Paving Co. in the amount of $1,532,539 and adding 40 working days for the change in scope of work; and,

C. Authorizing the City Manager to execute the necessary documents; and,

D. Authorizing the Finance Officer to make any necessary budget adjustments.

Body
ALTERNATIVES
1. Approve, as recommended by staff; or,
2. Approve, subject to conditions other than recommended by staff (identify specific findings and or/ conditions amended to be addressed in the motion); or,
3. Deny; or,
4. Refer to staff for reconsideration of specific items (specific items to be addressed in the motion); or,
5. Conti...

Click here for full text