File #: 19-073    Version: 1 Name:
Type: Consent Item Status: Passed
File created: 1/31/2019 In control: City Council/Public Finance and Economic Development Authority/Parking Authority/Successor Agency to the Redevelopment Agency
On agenda: 3/18/2019 Final action: 3/18/2019
Title: SUBJECT: Award of Bid and Approval of Construction Agreement with Rolfe Construction Company in the Amount of $968,802 for the Re-Bid of the Yosemite Avenue Leaf Collection Site, Project No. 116017 REPORT IN BRIEF Considers awarding a bid and approving an agreement in the amount of $968,802 with Rolfe Construction Company for City Project No. 116017 - Yosemite Avenue Leaf Collection Site. RECOMMENDATION City Council - Adopt a motion: A. Awarding the Yosemite Avenue Leaf Collection Site, Project 116017 to Rolfe Construction Company of Atwater, Ca, in the amount of $968,802.00; and, B. Authorizing the City Manager or the Assistant City Manager to execute the necessary documents and to approve change orders not to exceed 10% of the total contract; and, C. Authorizing the Finance Director to make necessary budget adjustments.
Attachments: 1. Location Map, 2. Bid Results.pdf, 3. Construction Contract
Report Prepared by: John Ainsworth, Temporary Senior Engineer, Engineering Division

Title
SUBJECT: Award of Bid and Approval of Construction Agreement with Rolfe Construction Company in the Amount of $968,802 for the Re-Bid of the Yosemite Avenue Leaf Collection Site, Project No. 116017

REPORT IN BRIEF
Considers awarding a bid and approving an agreement in the amount of $968,802 with Rolfe Construction Company for City Project No. 116017 - Yosemite Avenue Leaf Collection Site.

RECOMMENDATION
City Council - Adopt a motion:

A. Awarding the Yosemite Avenue Leaf Collection Site, Project 116017 to Rolfe Construction Company of Atwater, Ca, in the amount of $968,802.00; and,

B. Authorizing the City Manager or the Assistant City Manager to execute the necessary documents and to approve change orders not to exceed 10% of the total contract; and,

C. Authorizing the Finance Director to make necessary budget adjustments.

Body
ALTERNATIVES
1. Approve, as recommended by staff; or,
2. Reject all bids and direct Staff to rebid the project; or,
3. Continue to a future meeting (date and time to be specified in the motion).

AUTHORITY
Charter of the City of Merced, Article XI, Section 1109 - Contracts on Public Works, and Merced Municipal Code Chapter 3.04, Article IV - Public Works Contracts.

CITY COUNCIL PRIORITIES
As provided for in the 2018-19 Adopted Budget.

DISCUSSION
The work to be done consists, in general, of the demolition, clearing and grubbing of an existing rock sales yard and to install the improvements for a City operated street sweeping/leaf collection transfer site.

Items include the removal of concrete, asphalt paving, concrete bins, removal of septic system, fencing, and the installation of new fencing, concrete pads, a street sweeper dump structure, asphalt paving, water, sewer and storm drain improvements.

Staff revised the plans and specifications, reducing the project scope, and the project was re-advertised for bids in December 20...

Click here for full text