File #: 20-513    Version: 1 Name:
Type: Consent Item Status: Passed
File created: 9/4/2020 In control: City Council/Public Finance and Economic Development Authority/Parking Authority/Successor Agency to the Redevelopment Agency
On agenda: 10/19/2020 Final action: 10/19/2020
Title: SUBJECT: Award of Bid and Approval of Construction Contract with Rolfe Construction Company, Inc., in the Amount of $1,839,263.00, for a Sewer Funded Project for the Gerard Avenue Sewer from Highway 99 to Water Well 10-R2 (Kibby Road), Project No. 117020 REPORT IN BRIEF Considers awarding a construction contract in the amount of $1,839,263.00 funded by Sewer Enterprise funds for City Project No. 117020 - Gerard Avenue Sewer from Highway 99 to Water Well 10-R2 (Kibby Road). RECOMMENDATION City Council - Adopt a motion: A. Awarding the Gerard Avenue sewer from Highway 99 to Water Well 10-R2 (Kibby Road), Project 117020, to Rolfe Construction Company, Inc., in the amount of $1,839,263.00 and, B. Authorizing the Interim City Manager to execute the necessary documents and to approve change orders not to exceed 10% of the total contract.
Attachments: 1. Location Map.pdf, 2. Bid Results.pdf, 3. Construction Contract
Report Prepared by: Michael R. Beltran II, PE, City Engineer

Title
SUBJECT: Award of Bid and Approval of Construction Contract with Rolfe Construction Company, Inc., in the Amount of $1,839,263.00, for a Sewer Funded Project for the Gerard Avenue Sewer from Highway 99 to Water Well 10-R2 (Kibby Road), Project No. 117020

REPORT IN BRIEF
Considers awarding a construction contract in the amount of $1,839,263.00 funded by Sewer Enterprise funds for City Project No. 117020 - Gerard Avenue Sewer from Highway 99 to Water Well 10-R2 (Kibby Road).

RECOMMENDATION
City Council - Adopt a motion:

A. Awarding the Gerard Avenue sewer from Highway 99 to Water Well 10-R2 (Kibby Road), Project 117020, to Rolfe Construction Company, Inc., in the amount of $1,839,263.00 and,

B. Authorizing the Interim City Manager to execute the necessary documents and to approve change orders not to exceed 10% of the total contract.

Body
ALTERNATIVES
1. Approve, as recommended by staff; or,
2. Approve, subject to conditions other than recommended by staff (identify specific findings and/or conditions amended to be addressed in the motion); or,
3. Deny; or,
4. Refer to staff for reconsideration of specific items (specific items to be addressed in the motion); or,
5. Continue to a future meeting (date and time to be specified in the motion).

AUTHORITY
Charter of the City of Merced, Article XI, Section 1109 - Contracts on Public Works, and Merced Municipal Code Chapter 3.04, Article IV - Public Works Contracts.

CITY COUNCIL PRIORITIES
As provided for in the 2020-21 Adopted Budget.

DISCUSSION
The work to be done consists of the removal of the existing sewer trunk main and the installation of a new sewer trunk main on/adjacent to Gerard Avenue from Highway 99 to Well Site 10-R2 (Kibby Road).
Staff prepared plans and specifications, and bids were opened on October 6, 2020, with a total of three (3) bid submissions:

1. Rolfe Construction Company, Inc. $ 1,839,263.00
2. Mid Cal P...

Click here for full text